( ) risks cannot be management proactively and therefore may be assigned a management reserve.
A. Know
B. Natural
C. Unknown
D. Human
Earned value management(EVM) integrates the scope baseline with the ( ) baseline, along with schedule baseline,to form the performance baseline, which helps the project management team assess and measure project performance and progress.
A. quality
B. risk
C. change
D. cost
( ) are those costs that cannot be directly traced to a specific project and therefore will be accumulated and allocated equitably over multiple projects by some approved and documented accounting procedure.
A. Direct costs
B. Operation costs
C. Indirect costs
D. Implement costs
( ) is an open, distributed ledger that can record transactions between two parties efficiently and in a verifiable and permanent way.
A. Internet of things
B. Blockchain
C. Edge computing
D. Artificial intelligence
The( ) creates opportunities for more direct
integration of the physical world into computer-based systems, resulting in efficiency improvements, economic benefits, and reduced human exertions.
A. internet of things
B. cloud computing
C. big data
D. mobile internet
项目经理制定了项目资产负债表(单位:元),如下表所示。该项目的静态投资回收期为( )年,动态投资回收期为( )年。(保留一位小数位)
第 1 问
A. 2
B. 2.4
C. 2.8
D. 3
第 2 问
A. 3
B. 3.4
C. 3.5
D. 3.6