Earned value management(EVM) integrates the scope baseline with the (   ) baseline, along with schedule baseline,to form the performance baseline, which helps the project management team assess and measure project performance and progress.

A. quality

B. risk

C. change

D. cost

参考答案: D

详细解析:

挣值管理(EVM)将范围基线与(成本)基线以及进度基线集成在一起,形成性能基线,帮助项目管理团队评估和度量项目性能和进度。
A、质量
B、风险
C、变更
D、成本