The Develop Project Management Plan Process includes the actions necessary to define, prepare, integrate, and coordinate all constituent plans into a ( ) .
A. Project Scope Statement
B. Project Management Plan
C. Forecasts
D. Project Charter
Schedule development can require the review and revision of duration estimates and resource estimates to create an approved ( ) that can serve as a baseline to track progress.
A. scope statement
B. activity list
C. project charter
D. project schedule
The project life-cycle can be described as ( ).
A. project concept, project planning, project execution, and project close-out
B. project planning, work authorization, and project reporting
C. project planning, project control, project definition, WBS development, and project termination
D. project concept, project execution, and project reporting
Risk management allows the project manager and the project team not to( ).
A. eliminate most risks during the planning phase of the project
B. identify project risks
C. identify impacts of various risks
D. plan suitable responses
在制定项目质量计划时对实现既定目标的过程加以全面分析,估计到各种可能出现的障碍及结果,设想并制定相应的应变措施和应变计划,保持计划的灵活性。这种方法属于( )。
A. 流程图法
B. 实验设计法
C. 质量功能展开
D. 过程决策程序图法