( ) techniques are used to find ways to bring project activities that are behind into alignment with the plan by fast tracking or crashing the schedule for the remaining work .
A. Schedule forecasts
B. Schedule compression
C. Change requests
D. Data analysis
参考答案:
B
详细解析:
(进度压缩)技术用于通过快速跟踪或剩余工作的计划来找到使落后的项目活动与计划保持一致的方法。
A 进度预测 B 进度压缩
C 变更请求 D 数据分析